Preliminary Construction Activities Continue

Site clearing that started mid March was completed on April 17. At the beginning of this week, on Monday, April 20th, soil foundation investigations were begun. Completion of these investigations, as well as a site survey, is scheduled by May 8th. We will keep you updated on project activities as they progress.

21 views

Recent Posts

See All

Site Clearing Complete

May 8, 2020 marked the end of site clearing, as well as the soil foundation investigation and the topographic survey. The project is now moving forward to the full clearing and grading plan, followed

Site Clearing Begins

Site clearing activities for the construction of the Nevis Geothermal Plant begin tomorrow, 12 March, 2020. We will continue to keep you informed of activities and progress.