Nevis Geothermal Drilling Surpasses Halfway Mark


As of February 27th, the Nevis Geothermal Project surpassed the halfway point of 2,001 feet. The drilling operations team has been working on 24 hour shifts to speed up efforts towards achieving Nevis' overall goals of energy independence, security and resilience.


42 views

Recent Posts

See All

Site Clearing Complete

May 8, 2020 marked the end of site clearing, as well as the soil foundation investigation and the topographic survey. The project is now moving forward to the full clearing and grading plan, followed

Site Clearing Begins

Site clearing activities for the construction of the Nevis Geothermal Plant begin tomorrow, 12 March, 2020. We will continue to keep you informed of activities and progress.